PARE HYDRO POWER STATION (PHPS)

Energy Assets Imgae
PARE HYDRO POWER STATION (PHPS)
Category Page assets
id
3
Location Assets
Dist- Papum Pare, Arunachal Pradesh
Total Capacity(MW)
110
Status
Installed Capacity(MW)
2 x 55
Introduction

Introduction

Pare Hydro Power Station is a run-of-the river scheme to harness the hydro power of Dikrong River (a tributary of river Brahmaputra) and located at Sopo, Papum Pare District, Arunachal Pradesh. The Station also utilizes the Tail race discharge of the 405 MW Ranganadi Hydro Power Station. The installed capacity of the Plant is 110 MW with a catchment area of 824 Sq. Km and design head of 67.36m.

Features

Features

PARE HYDRO POWER STATION (PHPS)
NamePARE HYDRO POWER STATION (PHPS)
Capacity110 MW
Break Up Capacity

110 MW (2x55MW)

LocationDist- Papum Pare, Arunachal Pradesh,
ApproachBy Road -40 KM From Itanagar, Arunachal Pradesh
Design Energy

506.42 MU

Date of Commercial Operation (COD)
Unit-I --- 28th May 2018 
Unit-II --- 21st May 2018 
Beneficiary States / UTsAssam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland, Tripura
Technical Features
DamConcrete Gravity, Height :: 63 m, Length :: 134.275 m
FRL245.15 m
MDDL240 m
Design Head67.36 m
PenstockPr. Tunnel Gross Length 225 m, Dia. 6.4 m, Bifurcated (penstock) Dia. 4.5 m
HRTModified Horse Shoe Type
Length : 2818.73 m
Dia. :   7.50 m
Surge ShaftRESTRICTED ORIFICE TYPE/ Non Over flow, 57.29 m Depth, 18 m Dia.
Power HouseSurface, 2 no. Vertical Francis Turbine (55 MW)
Generator 2 no. Semi-Umbrella Type, Rated Voltage- 11 KV
Generator Step Up Transformer3-phase, 68MVA, 11/132 KV
Switchyard132 KV Air Insulated Substation (AIS)
Evacuation System132 kV S/C Pare-NLP line, 132 kV S/C Pare-Nirjuli line, 132 kV S/C Pare-Ranganadi line and 132 kV S/C Pare-Chimpu line
Achievements

Achievement

The Hon’ble Prime Minister of India dedicated the 110 MW Pare HEP to the Nation on 9th February 2019.

Pare Hydro Power Station (PLHPS) achieved annual generation exceeding the design energy (506.42) during FY 2020-21 and FY 2022-23 recording  generation of 522.29 MU and 531.843 MU respectively.

Status of Generation

Status of Generation

S.NoDescriptionGeneration (MU)Details
1Generation for the Month of Aug 202449.8370 MUGeneration for the month of Aug' 2024
2Total Generation from April, 2023 upto August, 2024671.8493 MUTotal Generation from April, 2023 upto August, 2024
3Total Generation during Financial Year 2022 to 2023531.8433 MUGeneration during F/Y 2022 to 2023
Contact Person
Contact Person

Project Head

Shri Harihar Medhi

Designation

General Manager (Tech) / HOP

Telephone (O)

7005245780

E-Mail

hoppare[at]neepco[dot]co[dot]in
image banner
PARE HYDRO POWER STATION (PHPS)
Map lat
27.2241
Map long
93.5003
Select map state
map icon
Pare Hydro Power Station (Phps)
Map Project name
Pare Hydro Power Station (Phps)