- he project was earlier withdrawn from NEEPCO in 2004 and now has been re-allotted.
- NEEPCO signed MOA with Govt. of Mizoram on 10.02.2015 for execution of the project.
HYDRO
- MOA was signed with State Govt. on 20.04.2012.
- Draft DPR for an installed capacity of 75 MW was submitted to CEA for scrutiny by CEA.
- As observed by CEA, the DPR is under revision for an installed capacity of 85 MW.
- Comprehensive environmental studies are in process.
Testing future project
- MOA was signed with State Govt. on 26.03.2010.
- Clearance of MEA for taking up the S&I works is awaited since both the projects involve international issue with Myanmar.
- MOA was signed with State Govt. on 26.03.2010.
- Clearance of MEA for taking up the S&I works is awaited since both the projects involve international issue with Myanmar.
- The project was earlier withdrawn from NEEPCO in 2004 and now has been re-allotted.
- NEEPCO signed MOA with Govt. of Mizoram on 10.02.2015 for execution of the project.
- Alternative study is in process to make the project economically viable.
- MOA was signed with State Govt. on 26.03.2010.
- After taking over the balance works of DPR preparation from CWC in 2014-15, DPR was prepared for an installed capacity of 17 MW and is under examination.