- Techno-Economic Clearance (TEC): Revalidation of CEA Concurrence up to 30.09.2027 was granted by CEA on 19.11.2025, subject to an updated hydrological assessment.
- Environmental Clearance (EC): Public hearing for Siang District and Shi Yomi District has been completed.
- Forest Clearance (FC): Project Screening Committee – I & II recommended the project for FC-I. As per observations of DFO during the site, the revised CAT plan has been submitted to the DFO, Along.
- Social Impact Assessment (SIA) Study approved by GoAP.
- Assessment survey for Shi-Yomi District and Siang District are in progress.
- Clearance from Ministry of Home Affairs (MHA): MHA clearance obtained 18.11.2025.
- Clearance from Ministry of Defence: MOD clearance obtained on 21.01.2026.
- Investment Approval: PIB memo shall be submitted after approval of updated cost estimates by CEA & CWC which is under process.
Sl. No
2
State
Arunachal Pradesh
Commissioning Schedule (Tent. From Investment Approval)
72 months