- Detailed Topographic and Hydrographic Survey completed.
- Detailed Project Report (DPR) is under preparation.
- Water availability and sedimentation study approved.
- EIA & EMP Study and Drilling & Drifting works are in progress.
Sl. No
4
Project Name:
State
Arunachal Pradesh
Commissioning Schedule (Tent. From Investment Approval)
60 months
Power project map potential
Status
6.5 years (Commissioning Schedule -- Tent. From Investment approval)
Projects in Pipeline Type
Installed Capacity(MW)
330
Map lat
94.7277
Map long
28.2179