Arunachal Pradesh

  • Detailed Topographic and Hydrographic Survey completed.
  • Detailed Project Report (DPR) is under preparation.
  • Joint Venture formed in 2014 between NEEPCO and KSK Energy Ventures Ltd.
  • Post TEC recommendation on Environmental flow as per Basin Study Report induced modification in some TEC parameters. 
  • Site-specific e-flow study undertaken as advised by CEA outcomes of which shall be considered for re-assessment of project parameters subject to approval by MOEF&CC.

Introduction

Kameng Hydro Power Station is a run-of-the river scheme to harness the hydro power of Bichom and Tenga Rivers (both tributaries of the River Kameng) with the Power House located at Kimi, West Kameng District, Arunachal Pradesh. The Power Station has two Dam, one at Bichom & the other at Tenga. The installed capacity of the Station is 600 MW with a catchment area of 2277 Sq. Km (Bichom) & 1019 Sq. Km (Tenga) and design head of 504 m.